When I update my project with new information I input the status date (same as current date in my case) and all the corresponding task information. Often I have tasks that should have been completed by the status date which haven't even been started. Project just leaves them behind the current date line and therefore the finish date is unrealistic. If I try to push the task out it puts a constraint on the task which I am trying to avoid. Seems like project should just realize that any work not done yet will have to be rescheduled for after today. What am I doing wrong? I have checked tools/option/calculation and the automatic is checked.