Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations IamaSherpa on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Hi all, I hope someone will be a

Status
Not open for further replies.

zi1

IS-IT--Management
Aug 3, 2012
2
CA
Hi all,

I hope someone will be able to clarify this for me:

I am using Project to track work and schedule.

Let's say I have a task (type = Fixed work) that has 8 hours of work and 1 resource allocated at 100% units and the calendar working time is 8hours per day. Let's say the resource has spent 8 hours, but still has 4 more hours of work, and that he tells me he will be able to finish it only 2 days from today.

What I do then is update the actual hours with 8, and update the remaining hours with 4. Then, since my resource is 100% allocated, Ms Project calculates that it would finish the work tomorrow. However, I know the resource won't be able to finish it only 2 days from now. So, what I do is update the Finish Date to the day after using the Assignment Information Dialog Box (Task Usage > Uncollapse the task > Double-click on the resource Name).

In this scenario, I would expect to see the Units for my resource automatically get recalculated by Ms Project once I click Ok. However, what I see now, is a resource that is 100% allocated, even though the amount of work scheduled for each day is less than 8 hours.

Anyone could please help clarify why I am seeing such behavior, is it expected? If so, how should I update my project plan in that scenario? Would updating the units instead of Finish date, until I reach the finish date I am expecting be the solution?

Thanks for your help,

Zi.
 
Hi Zi,

I'm guessing you are using Project 2010. The value you see in the Assignment Information dialog box, is the initial assignment unit of 100%. Even if you add Peak to the left side of the Task Usage view you will see 100% - as that is the highest peak for the assignment. Best option is to add Peak to the right (timescaled) side of the view and you should see the drop in peak units for the remaining work on the assignment.

I hope this helps.

Julie
 
Thank you Julie for your quick response. That answers my question, thank you!!

Zi.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top