Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Mike Lewis on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Help, my MS Project is crazy

Status
Not open for further replies.

pepas

Technical User
May 20, 2013
3
Hi guys,

I recent installed the MS Project 2007 and I can't get this calendar straight. My project is detailed in consecutive days and I'm trying to enter these on the software but it keeps considering Sunday as a non-working day. I've changede the working days, created a new calendar and everything but, it doesn't work. For an example: the first item starts in May 13th and it lasts 225 consecutive days. It should end on December 24th but it is ending on November 28th. What to do?
 
You might send a screen shot of your custom calendar; also the Advanced tab of the Task Information dialog. That's usually the method to ensure consecutive days. You've probably just missed something in the mix.

Scott
 
What is the definition of working time (Tools > Change Working time) in your project. 8:00 - 5:00 pm Monday through Saturday? What is the definition of "Day" and Week - check Tools > Options, Schedule.
 
Guys, I panicked out and started it over. I don't know why, but everything is ok now! thx anyway
 
Please make sure you have all service packs installed to Project 2007 - Service Pack 3 is the most recent.
 
I have it installed. Maybe I just did something wrong in the beginning but now it's cool.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top