Hi guys,
I recent installed the MS Project 2007 and I can't get this calendar straight. My project is detailed in consecutive days and I'm trying to enter these on the software but it keeps considering Sunday as a non-working day. I've changede the working days, created a new calendar and everything but, it doesn't work. For an example: the first item starts in May 13th and it lasts 225 consecutive days. It should end on December 24th but it is ending on November 28th. What to do?
I recent installed the MS Project 2007 and I can't get this calendar straight. My project is detailed in consecutive days and I'm trying to enter these on the software but it keeps considering Sunday as a non-working day. I've changede the working days, created a new calendar and everything but, it doesn't work. For an example: the first item starts in May 13th and it lasts 225 consecutive days. It should end on December 24th but it is ending on November 28th. What to do?