Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations IamaSherpa on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Help % complete doesn't reflect reality

Status
Not open for further replies.

jdmorrisn

Technical User
Aug 23, 2012
1
EE
Hi all, i have Project 2003, I'm not an expert and I generally get by (it isn't that important for my job however from time to time it is necessary).

I have a problem that i have one project which has lots of installations, in the beginning requiring more man hours and getting easier toward the end. Currently we are 50% through the project but the % complete column shows much less being based on duration, however the duration really isn't accurate since it might have 10 days for a certain task but that task takes 15 men. Whereas later tasks have 10 days but they are for 1 man. So you see, it doesn't balance out accurately using this method. How the hell can I do it to more accurately reflect the actual completion as opposed to the duration.

As a clear example; if I were to decrease the duration of a task to say 2 days each instead of 16 days the ‘percentage complete’ column of the project would reduce - however completing tasks in a faster time than the duration estimated obviously does not mean that the project is less complete, but rather the opposite. So you see; this column is not a true reflection of the progress so far. Likewise if I were to increase the time it takes to do a task to 20 days each it would increase the ‘% complete’ column.

I'm going nuts here and can't find anything on the web to help. And please keep the jargon for a numpty like me :)

 
Hi,

If you have assigned resources to the tasks, you can use the % Work Complete to more accurately reflect progress. % complete is a duration measure where % work complete is a work measure. There is a tie between % complete and % work complete -- if you increase duration, Project will assume there is more work.

I hope this helps.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top