Hello ,
our CE system is in use for automatic scheduling on demand by passing more that 100 schedule tasks every night. The scheduling time is set to "now", so that the jobserver actually should schedule step by step all tasks.
But sometimes the APS forgets one report schduling task and schedules one ore two of all 7 hours to late !)
For example the startTime of one report is
2003.07.30-03:14:21 the jobserver scedules this one at 12 o'clock, where from 4 - 12 o'clock the aps does nothing..
Are there some hidden parameters to optimize mass - scheduling (mass scheduling in a short time range) ??
.. our jobserver scheduls only 2 reports at the same time. Thats full enough, because one report needs not more than 3 minutes and all mass schedule tasks are done after one hour, until one that needs 7 hours to wake up
rgs Andre
our CE system is in use for automatic scheduling on demand by passing more that 100 schedule tasks every night. The scheduling time is set to "now", so that the jobserver actually should schedule step by step all tasks.
But sometimes the APS forgets one report schduling task and schedules one ore two of all 7 hours to late !)
For example the startTime of one report is
2003.07.30-03:14:21 the jobserver scedules this one at 12 o'clock, where from 4 - 12 o'clock the aps does nothing..
Are there some hidden parameters to optimize mass - scheduling (mass scheduling in a short time range) ??
.. our jobserver scheduls only 2 reports at the same time. Thats full enough, because one report needs not more than 3 minutes and all mass schedule tasks are done after one hour, until one that needs 7 hours to wake up
rgs Andre