having start and end time instead of date in MS project

Status
Not open for further replies.
Mar 21, 2013
3
US
Hi members,
I want to know if we can have start and end time instead of date because tasks are small and have multiple tasks in one day.

Nishant
 
You may change the display of dates in Project to include time through File > Options, General. Select a Date Format showing date and time.

Julie
 
BTW, Date and time are inextricably conjoined. They are both a part of the same stuff. FORMAT your Date/Time values as desired.