Hi. I am very much a MS Project noob and I have two questions about this simple project (attached) which are really bugging me:
1. why does it say my resource is over allocated (when it isn't - look at task ID 23, working 1 hour on a workday)
2. I put together steps of an outlined project (starting at ID 20) which has a duration of 235 hours, but "Work" is totaling 300 hours -- why the gap?
Additionally, from an expert eye, is there anything I'm majorly screwing up about this file? The project is basically my work week over the past two weeks plus a coming project.
1. why does it say my resource is over allocated (when it isn't - look at task ID 23, working 1 hour on a workday)
2. I put together steps of an outlined project (starting at ID 20) which has a duration of 235 hours, but "Work" is totaling 300 hours -- why the gap?
Additionally, from an expert eye, is there anything I'm majorly screwing up about this file? The project is basically my work week over the past two weeks plus a coming project.