Bigfish311
Technical User
I have been working with multiple project scheduling tools and have an issue with MS Project. In Primavera you can put a constraint on an activity to carry zero free float so it will always be smack up against it's successor. In Project you can put the start as late as possible constraint on an activity but it will then push on it's successor to eat up all of it's float. I just want the preceding activity to flow right up against the successor, and let the successor start as soon as possible so the successor can still keeps it's own total float. I'm sure there something I'm skipping over here. Thanks guys.