CornishPlanner
Technical User
Hi Guys I am new and hoping you can help. I have a scenario where we have been asked by the client to price for extra works so we are also obliged to enter them into the programme. Unfortunately they go beyond the end of the current critical path and the end date of the project. As they are separate items that will not effect the contractual completion I have not linked them in anyway to the project end task however Project seems to mark any task that has a completion later than the end date as critical path and this also removes the critical path from the current position. I am aware you can also show CP's by adding days to the also show critical with X days slack but this will not remove the additional tasks from the CP. Any ideas? I don not wish to show these tasks on an additional programme and worst case scenario I will manually colour the tasks or increase the slack period and colour the new CP blue. I hope this ,makes sense and I am using 2003 cheers Alex