Have 0 as for WBS ID?

Status
Not open for further replies.

DEPM

Technical User
Jun 9, 2012
12
Hi,

How can I have 0 (zero) as my first WBS ID? I did on past projects, but I don't recall how I did it before, since I've been away from MS Project for a while.

Now, using MS Project 2010.

Thanks
DEPM

Design Engineer Project Manager (DEPM)
 
Line zero is the Project Summary task. If you are using Project 2010, click the Format tab, and select "Project Summary Task" in the Show/Hide Group. You may also enable it for all projects in File > Options, Advanced - Display options for "All Projects"