hi
I cant seem to find answer to my question ( but my apologies if this has been answeredvefore)so here goes
I would like to have groups of resources
ie
Engineers, welders etc, each group would have a max number eg 10 mech
engineers 10 elec engineers, 20 welders etc
when allocating resource rather than individuals I would like to
allocate a number from the total resource for that disciple
ie task A requires 4 welders 2 mech I elec,
and then when leveling the resource we would level against the pool total
its probably pretty simple but I'm not that experienced with MSP
any suggestion would be grateful
I cant seem to find answer to my question ( but my apologies if this has been answeredvefore)so here goes
I would like to have groups of resources
ie
Engineers, welders etc, each group would have a max number eg 10 mech
engineers 10 elec engineers, 20 welders etc
when allocating resource rather than individuals I would like to
allocate a number from the total resource for that disciple
ie task A requires 4 welders 2 mech I elec,
and then when leveling the resource we would level against the pool total
its probably pretty simple but I'm not that experienced with MSP
any suggestion would be grateful