I'm creating a conversion day plan and want to show the times for the tasks and not the dates (as everything should happen on one day). I have managed to change the duration to show in minutes, but how do I get the start/finish columns on the GANT chart to show time rather than date.

Thanks
 
You can right-mouse click on the Gantt chart and select "Layout". Change the Date Format on the bars from the pull-down list examples.
 