Billythekangaroo
IS-IT--Management
My projects normally are not planned or costed to work weekends.
I can get the initial Gantt chart bars to look OK by making Project calendar five days and non-working time appear in fromt in bars - which look great.
However, there are exceptional circumstances where tasks must be worked on at weekend.
I can create a six ( or seven ) day calendar to achieve this by assigning tasks to this new calendar which makes the elapsed time OK but they may be obscured by non-working time as above..
I want the client to see a Gannt chart with normal tasks not working at weekend but special tasks do.
This seems an obvious requirement - what am I missing ?
HELP
I can get the initial Gantt chart bars to look OK by making Project calendar five days and non-working time appear in fromt in bars - which look great.
However, there are exceptional circumstances where tasks must be worked on at weekend.
I can create a six ( or seven ) day calendar to achieve this by assigning tasks to this new calendar which makes the elapsed time OK but they may be obscured by non-working time as above..
I want the client to see a Gannt chart with normal tasks not working at weekend but special tasks do.
This seems an obvious requirement - what am I missing ?
HELP