CalicheClay
Technical User
I use MS Project to create estimates based on timelines, by resource loading a project, and using the cost column to generate expected cost.
The problem I have is that for resource cost, you are given the option of either standard rates, or cost/use. The standard rate takes into consideration partial units of duration. In the real world, a contractor will most likely charge you for a full day of work even if they were onsite for a partial day.
Is there any way to set up Project to calculate a full day of work for a partial day of duration? Example:
Task is 3 days and 6 hrs long. The contractor charges $4,000/day. Project will calculate 3.25 days X $4,000 = $13000. I want it to calculate $4,000 X 4 days = $16000. The partial day should be calculated as a full day, but should not impact the duration of the project.
Thanks!
The problem I have is that for resource cost, you are given the option of either standard rates, or cost/use. The standard rate takes into consideration partial units of duration. In the real world, a contractor will most likely charge you for a full day of work even if they were onsite for a partial day.
Is there any way to set up Project to calculate a full day of work for a partial day of duration? Example:
Task is 3 days and 6 hrs long. The contractor charges $4,000/day. Project will calculate 3.25 days X $4,000 = $13000. I want it to calculate $4,000 X 4 days = $16000. The partial day should be calculated as a full day, but should not impact the duration of the project.
Thanks!