I need to have tasks that have a duration that exceeds the work of the resource assigned eg task duration is 5 days, resource effort is 2 man days.
I would like MSP to front-load the resource ie in the example above the two man days would occur on days 1 and 2 of the 5-day task.
If I use fixed duration, MSP will keep the task to 5 days, but will allocate the effort across the duration, .4 of a man day each day.
How can I front load? The only method I can find is to manually schedule the resource effort in the task usage view, which is laborious. Using the Front-Loaded work contour creates some wierd profile but does not front-load as I have defined it.
Any assistance gratefully appreciated.
I would like MSP to front-load the resource ie in the example above the two man days would occur on days 1 and 2 of the 5-day task.
If I use fixed duration, MSP will keep the task to 5 days, but will allocate the effort across the duration, .4 of a man day each day.
How can I front load? The only method I can find is to manually schedule the resource effort in the task usage view, which is laborious. Using the Front-Loaded work contour creates some wierd profile but does not front-load as I have defined it.
Any assistance gratefully appreciated.