YANKRAY
Technical User
- Nov 7, 2003
- 283
Using MS Project 2007.
Can Project calculate the Finish date for a task based on the current % complete entered?
For example. If a task is scheduled to be completed today but is only 50% complete, can project calculate the completion date where the percent complete indication would show on schedule but the task completion would extend out?
The baseline would show where the task should have completed. I would like to see Project readjust the schedule and determine a new finish date for the tasks and the project based on the % completes and all the Predecessors within the project.
Thanks,
Ray
Can Project calculate the Finish date for a task based on the current % complete entered?
For example. If a task is scheduled to be completed today but is only 50% complete, can project calculate the completion date where the percent complete indication would show on schedule but the task completion would extend out?
The baseline would show where the task should have completed. I would like to see Project readjust the schedule and determine a new finish date for the tasks and the project based on the % completes and all the Predecessors within the project.
Thanks,
Ray