Hi,
I inserted or imported multiple project schedules into 1 master schedule file by using Insert Subproject which works great!
Now, is there a way to verify or find it's directory path?
Also, if imported projects changes, perhaps, with new file name, is there an easier way to update master file instead of removing old version & adding newer version in?
Thanks