VVAC123

Technical User
Nov 27, 2009
17
US
Is there any way to filter for a tasks without the summery task showing , only want to see the task not the summary tasks, i added afield "Marked" yes or no choices when filter for yes the summery task with now still show in the chart.....
Thanks
VVAC
 
Are you serious?

Apply the filter
Tools > Options > View-tab and clear the box "Show summary tasks"

If you want to make that the default behaviour then it gets stunningly complicated

Project > Filtered For:xxx > More filters
Select the filter
Click on edit
Clear the box labelled "Show summary rows
 