Ok I am new so any help is much appreciated.

I have a master project which is my resource pool.

Inside this master I have two projects (inserted) each with a couple sub-projects (inserted projects).

When I want to level the resources for a particular sub-project is there a way to do this from the top most master project? I mean can I see resource usage/hours per resource for just that sub-project from within the master project resource usage view or should I open the sub-project itself to see just the resource usage for that sub-project, edit, save and then go back to the master project to see the over all view?

I guess in a sence I am asking if there is a way to filter my master projects recource usage view to a particular sub-project so that I can only see hours for the sub and manually work on leveling for that particlar sub-project alone.
 
sorry my subject line should say ... Filter Resource Usage in MASTER Project?

It's what I get for working when I am tired LoL
 