Look at the book... sometimes it is very useful
In your case
555-233-118
Comcode 108678657
Issue 1
April 2000
DEFINITY ®
Enterprise Communication Server
Release 8.2
Installation, Upgrades, and Additions for
Compact Modular Cabinets
Just a little fragment from CD-docs:
".....Wall-Mount the Cabinets
Install Plywood Backing onto Wall
The plywood and the hardware to mount the plywood are installer-provided.
NOTE:
The following plywood dimensions account for the extra space needed to
install the panels on each side of the cabinet. The cabinet is 24 in. (0.6 m)
wide and each panel is 12 in. (0.3 m) wide.
Single-Cabinet Installation
1. Install a 3/4-in. (2 cm) thick sheet of 2 x 4-ft (0.6 x 1.2 m) plywood
horizontally onto the wall. See Figure 1-4.
The top of the plywood must be at least 54 in. (137 cm) from the floor.
2 or 3 Vertically Mounted Cabinets
1. Install a 3/4-in. (2 cm) thick sheet of 4 x 8-ft (1.2 x 2.4 m) plywood vertically
onto the wall. See Figure 1-6.
2 Cabinets Vertically Mounted and 1 Cabinet Horizontally Mounted
1. Install a 3/4-in. (2 cm) thick sheet of 4 x 8-ft (1.2 x 2.4 m) plywood vertically
onto the wall. See Figure 1-6.
2. Install a 3/4-in. (2 cm) thick sheet of 2 x 4-ft (0.6 x 1.2 m) sheet of plywood
horizontally onto the wall. Position the plywood to the right of the first
sheet, across from Cabinet A."
Are you referring to an extra cabinet B,C or D. Or are you referring to an EPN 2nd A-carrier?
For an CSi or a same PortNetwork Si, you just have to install the flatcable between the cabinets.
For a Si EPN you have to interconnect the PPN A-carrier to the EPN A-carrier using the expansion interfaces by fiber or coax.