We have a task that fabricates a piece of equipment. The resources in human terms build up costs as they charge to the job. To set the baseline for our customer we also have to incorporate the cost of the sale of the piece of equipment completed at the end of the task as a one time charge.
Can this type of dual cost collection be done?
We are also trying to understand incremental cost collection for the piece of equipment build as its a 6-8 month fabrication process and we get to charge for work incurred including partials against the material.
We want to use project as it is time based and EVMS is also time based such that if the schedule moves all the EVMS cost changes get tracked by the schedule changes/resource allocation changes.
Thanks in advance,
Bill
Can this type of dual cost collection be done?
We are also trying to understand incremental cost collection for the piece of equipment build as its a 6-8 month fabrication process and we get to charge for work incurred including partials against the material.
We want to use project as it is time based and EVMS is also time based such that if the schedule moves all the EVMS cost changes get tracked by the schedule changes/resource allocation changes.
Thanks in advance,
Bill