ETT tracking

Status
Not open for further replies.

ncc1701f

IS-IT--Management
Apr 21, 2003
1
CA
how can i use ett tracking to have a user submit a job to OPC that will have dependancies on applications in the current plan .
 
In the ett dialog do this:

name of triggering event should be the jobname that the user
submits. Id of associated appl. shoul be a application that yoc create. (this appl will be added to cp when user submits user job).
set colums like this:
E J D A
T R R S
-----------
J Y Y N

DR = Y means dependecy resolution = yes.

the application you create to include this user submitted job should use = period called ETTRCY1, and have the same or
earlier input arrival time as the applications it should have dependecies to.
first operation in appl should have the jobname of the user job.

 
Status
Not open for further replies.