Is there any way to enter a non linear task in MSP? In other words, if I have a task that lasts 8 weeks and 15% of the work is going to be done during each of the first 2 weeks, 5% per week for the next 4 weeks and the remainder divided amongst the last two weeks.
If this was entered normally, it would show being behind schedule weeks 3-6 when in reality it isn't.
Any suggestions?