I am making a construction schedule so I have durations for tasks such as framing a home 8 days. I want to view this on a daily basis and see what "workday" it is happening on. I guess expanded out? so it shows day 1,2,3,4 etc and what is happpening on each of those days so in the above example it would show framing eight times for the eight days and what work day it is like day 20-28 if those were the days they were occuring on.
 
Seems like a homework question to me.

View | Gantt
Format | Timescale
Middle tier - Units: Weeks; Label: W1, W2, W3, W4 ... (From Start)
Bottom tier - Units: Days; Label: D1, D2, D3 ... (From Start)
 