Howdy;
I am using MS Project 2003 SP2 and am having issues on the follows;
When entering in a task that has a start date of 8/4/2006, an end date of 8/11/2006. I expect 11 hours to be spent on this task between the dates already set. However, when I input the 11 hours, the start date changes to be 8/10/2006.
I wish to assign one resource to a number of different tasks over a set start and end time, and maintain the duration with the number I initiall input.
Is this clear? May anyone suggest something?
Thanks much!!
~wmichael
"small change can often be found under seat cushions
I am using MS Project 2003 SP2 and am having issues on the follows;
When entering in a task that has a start date of 8/4/2006, an end date of 8/11/2006. I expect 11 hours to be spent on this task between the dates already set. However, when I input the 11 hours, the start date changes to be 8/10/2006.
I wish to assign one resource to a number of different tasks over a set start and end time, and maintain the duration with the number I initiall input.
Is this clear? May anyone suggest something?
Thanks much!!
~wmichael
"small change can often be found under seat cushions