Hi, I'm new to MS Project 2010.
I want to know how to get Project to distribute a resource in such a way that it is not overallocated.
For example, I have Task A -takes 9 hours and Task B - takes 9 hours
I have only one person working a regular 8 hour shift.
For some reason, Project allocates Task A 8 hours on one day and 1 hour the next day.
Then task B also 8 hours on the same day and 1 hour on the next day.
How do I tell Poject to just continue allocating evenly, I dont't care how many days it takes, but just to use one resource.
I already set up FS dependency, but its still happening.
Basically, I want to not to have a end date, finish when ever possible but use limited resources.
Thanks
I want to know how to get Project to distribute a resource in such a way that it is not overallocated.
For example, I have Task A -takes 9 hours and Task B - takes 9 hours
I have only one person working a regular 8 hour shift.
For some reason, Project allocates Task A 8 hours on one day and 1 hour the next day.
Then task B also 8 hours on the same day and 1 hour on the next day.
How do I tell Poject to just continue allocating evenly, I dont't care how many days it takes, but just to use one resource.
I already set up FS dependency, but its still happening.
Basically, I want to not to have a end date, finish when ever possible but use limited resources.
Thanks