I am wanting to display my estimated duration (project baseline) and the actual duration (the time it actually took me to complete each task) seperately on the gantt chart for tasks.
I have tried setting my baseline and then adding the "actual duration" column, however whenever I enter the values for actual duration, it auto corrects my estimated duration.
I want to be able to compare the time I estimated how long the task would take and how long it actually took on the gantt chart.
Is this even possible? If so, how????????