Is there a way to display the baseline information for high level tasks? For example: I have
Task Group 1
Task 1.1
Task 1.2
Task 1.3
Task Group 2
Task 2.1
Task 2.2
Task 2.3
While I can see the baseline for tasks 1.1,1.2,1.3,2.1,2.2,2.3 but for Task Groups 1 and 2 it only shows progress and doesn't show the baseline for those tasks.
How can I get MS Project to display that please?
Thank you in advance,
Jay
Task Group 1
Task 1.1
Task 1.2
Task 1.3
Task Group 2
Task 2.1
Task 2.2
Task 2.3
While I can see the baseline for tasks 1.1,1.2,1.3,2.1,2.2,2.3 but for Task Groups 1 and 2 it only shows progress and doesn't show the baseline for those tasks.
How can I get MS Project to display that please?
Thank you in advance,
Jay