Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations strongm on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Display Baseline information for summary/high level task 1

Status
Not open for further replies.

sa02000

Technical User
Oct 18, 2011
3
US
Is there a way to display the baseline information for high level tasks? For example: I have

Task Group 1
Task 1.1
Task 1.2
Task 1.3
Task Group 2
Task 2.1
Task 2.2
Task 2.3

While I can see the baseline for tasks 1.1,1.2,1.3,2.1,2.2,2.3 but for Task Groups 1 and 2 it only shows progress and doesn't show the baseline for those tasks.
How can I get MS Project to display that please?

Thank you in advance,
Jay
 
If you're looking at the Tracking Gantt you won't see any Gantt bars for the summary tasks.

To see if the tasks were baselined, insert the Baseline Start column. If you see "NA" then it wasn't baselined; if you see a date then it was baselined.
 
Run the Gantt chart wizard to display baseline bars for summary tasks.

As long as the summary tasks (Task Group 1 in your example) have been baselined, the bar is available.

Julie
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top