theewizard
Technical User
I know there is or should be a way to use standard task codes for setting up timelines with successors and predecessors. Why would/should we have to use line numbers instead of task numbering. I am in a college class and we can't figure out how to do it. We enter the task number followed by the task or activity name. Then we enter the duration and the project start date. Next we go to the successors and have to assign the line numbers instead of the task numbers. This considerably complicates the thought process to substituting the line number from the task number making every job or at least jobs that vary in tasks a new exersize in numbering. There has to be a way to assign a custom numbering convention to be used this way.