Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations strongm on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

critical path starts from last milestone

Status
Not open for further replies.

Miko18

Technical User
Nov 10, 2002
2
GB
Ive created a project plan in Project 2000 (network chart), and I have milestones in it but the critical path will only start from the last milestone, is this it now, or is there a setting where this can be changed so the critical path can go through the entire network chart, not just from the last milestone?
 
I get the impression there is more that we aren't seeing with this issue. If you look at the Network diagram, there should be a red highlighted Critical Path throughout the plan. If not, then your tasks may be scheduled such that they all have some slack in them. You can create a table display to look at the early and late start/end dates and see for yourself.

Good Luck!
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top