Hi,
Slightly strange question but does anyone know of an alternative to the standard critical path analysis method (i.e. tasks - duration - dependencies - network diagram).
I am creating a programme plan, so by its very nature it does not have all the detailed tasks and dependencies in. Many of the tasks and milestones are dates taken from project plans and not calculated within the programme plan itself via durations and dependencies. Also many dates have constraint dates applied to get them into the plan - which breaks the natural scheduling (and critical path calculating) in MS Project.
However I do need to show the programme critical path.
Could anyone suggest a way of doing this or has done something similar in the past? It does not have to be a perfect method like CPM, but would just like something that I can consistently apply to the programme plan.
Any help greatly appreciated. Thanks
Slightly strange question but does anyone know of an alternative to the standard critical path analysis method (i.e. tasks - duration - dependencies - network diagram).
I am creating a programme plan, so by its very nature it does not have all the detailed tasks and dependencies in. Many of the tasks and milestones are dates taken from project plans and not calculated within the programme plan itself via durations and dependencies. Also many dates have constraint dates applied to get them into the plan - which breaks the natural scheduling (and critical path calculating) in MS Project.
However I do need to show the programme critical path.
Could anyone suggest a way of doing this or has done something similar in the past? It does not have to be a perfect method like CPM, but would just like something that I can consistently apply to the programme plan.
Any help greatly appreciated. Thanks