Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations SkipVought on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Creating a new baseline after changes in project scope

Status
Not open for further replies.

Soikkendaal

Technical User
Jan 29, 2013
11
0
0
FI
hi

here's my situation: have made a project plan with agreed tasks and duration and set a baseline. the project has been going on for several weeks and actual work reported.

now changes are needed (and approved by the steering): two extra resources are needed in the project because of an extra task (scope was changed). this also leads to a changge in the schedule.

how do a make a new plan with these changes and make a new baseline so that reporrted actual work still remains?

soili
 
I would copy the existing baseline into Baseline1 and then baseline the revised portion of the plan. I would not attempt to create a new plan - just use the "Save Baseline" command and the "interim plan" to preserve the original baselines and create a new one.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top