Count days between two dates??

Status
Not open for further replies.

Snooker07

Technical User
Nov 11, 2008
6
US
Hello and thank you!

I am sure this will be very simple for most all of you.

I need to count days beween two date ranges excluding weekends, for example:

04/28/2009 to 04/30/2009 Result should be 2


04/28/2009 to 05/04/2009 Result should be 3

Thank you and much appreciated.

Snooker

 


Hi,

Check out Analysis ToolPak add-in NETWORKDAYS function.

Skip,
[glasses]Don't let the Diatribe...
talk you to death![tongue]

[glasses]Just traded in my old subtlety...
for a NUANCE![tongue]
 
Have a look at NetWorkDays.

But notice that it would return 3 for your first example because it counts:
1) 04/28/2009
2) 04/29/2009
3) 04/30/2009

If you want to ignore the first day, then just subtract one.

[tt][blue]-John[/blue][/tt]
[tab][red]The plural of anecdote is not data[/red]

Help us help you. Please read FAQ 181-2886 before posting.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top