I have used the keyword search but am unable to find words that match what must be a common issue.
I have a resource pool and a project that are linked and the pool takes precedence. We thought that a resource at a remote site was working last week on the project, but had been redirected without our knowledge.
The project and pool resource sheet have him assigned to a project task that was five days long. When I go to the pool and put those dates in as unavailable, the pool/project will not release him from the original dates. I think this is because it is now in the past, because I have changed constraints trying to force the unavailability to start on Monday of last week, but the pool jumps it a week and continues to show work on the orignially assigned task. The completion bar has not been activated.
I could rename the resource and use a different spelling and that might work for scheduling, but it would throw off history.
How can I fix this?
I have a resource pool and a project that are linked and the pool takes precedence. We thought that a resource at a remote site was working last week on the project, but had been redirected without our knowledge.
The project and pool resource sheet have him assigned to a project task that was five days long. When I go to the pool and put those dates in as unavailable, the pool/project will not release him from the original dates. I think this is because it is now in the past, because I have changed constraints trying to force the unavailability to start on Monday of last week, but the pool jumps it a week and continues to show work on the orignially assigned task. The completion bar has not been activated.
I could rename the resource and use a different spelling and that might work for scheduling, but it would throw off history.
How can I fix this?