Hi,
I am trying to do the following:
I am copying and pasting about 300 lines from one workplan to another.
The master plan has 17,000 hours and when I was trying to copy and
paste the 300 lines from a new plan (lets call it plan A) into the
master, I am loosing 1,500 hours. When I did a contrast of the master
before and after the pasting, I notice that it messes up the hours on
certain resources on only certain deliverables.
Could you please advise what the issue could be? Plan A was created by
another team member, so is it something in his settings that making me
loose the resources and the hours?
Thanks,
Vidita.
I am trying to do the following:
I am copying and pasting about 300 lines from one workplan to another.
The master plan has 17,000 hours and when I was trying to copy and
paste the 300 lines from a new plan (lets call it plan A) into the
master, I am loosing 1,500 hours. When I did a contrast of the master
before and after the pasting, I notice that it messes up the hours on
certain resources on only certain deliverables.
Could you please advise what the issue could be? Plan A was created by
another team member, so is it something in his settings that making me
loose the resources and the hours?
Thanks,
Vidita.