Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Mike Lewis on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

constraint changes while switching from Manual to auto scheduling

Status
Not open for further replies.

tonew

Technical User
Feb 18, 2014
23
CA
Hello there, I have a project file where I have projects with set up as "schedule from project finish date" and "fixed work" and "must finish on" constraint. now I did some importing information to manually edit. Then when I am done and then I switched from manual to auto.Then My project constraint is changing from "Must finish on" to "Finish as late as possible" which is exactly opposite what I needed.I am flexible to move around my start date or duration or assign more o less resources.Even "finish as soon as possible" or "finish no later than" constraint will work.Seems like it is switching to a default constraint "ALAP".Could anyone plaese tell me if there is a way I could set up my project with constraint "must finish on" constraint.Please Help.It will be a big help.Thanks.
 
Manually scheduled tasks cannot be constrained. So, when you switch from auto to manual scheduling - the task inherits the default constraint of ALAP from a project scheduled from a finish date. If you want to set Must Finish On constraints, the task must be autoscheduled.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top