I don't think this is possible, but still an interesting thought.
My project has significant boards that will be making Go/No-Go decisions before Go Live. The first meets on a Tuesday. Is there any way to constrain it so that it retains the dynamic relationship i.e if it gets pushed to the right past Tuesday, the start date moves to the subsequent Tuesday?
Thanks
Simon