I am using Project 2000 SR1 with Central SR1. When I
assign a task using team assign it updates the confirmed
field to Yes instead of Response pending (as per the
help).

Is this a known bug or has anyone seen it before and know
how to get around it?

Alex
 
Microsoft say this is expected behaviour - very useful !