Hi everyone,
We have a task in a schedule that was entered as a fixed-duration task. There are no resources assigned to the task, the task has no predecessors, and no tasks rely on this task as a predecessor.
The duration of the task was set to 25 days. When we went to update the % Complete field for the task from 16% to 40%, Project changed 40% to 100%. 40% also seems to be the threshold for this happening...i.e. if we change the % Complete to 35%, Project keeps it at 35%, but at 40% it bounces to 100%.
Any ideas why this may be happening? I noticed that if we change the task to a fixed unit task type, this doesn't happen. I've been poring over work formula calculations in a guide to MS Project but I'm still stumped.
-jjmclell
We have a task in a schedule that was entered as a fixed-duration task. There are no resources assigned to the task, the task has no predecessors, and no tasks rely on this task as a predecessor.
The duration of the task was set to 25 days. When we went to update the % Complete field for the task from 16% to 40%, Project changed 40% to 100%. 40% also seems to be the threshold for this happening...i.e. if we change the % Complete to 35%, Project keeps it at 35%, but at 40% it bounces to 100%.
Any ideas why this may be happening? I noticed that if we change the task to a fixed unit task type, this doesn't happen. I've been poring over work formula calculations in a guide to MS Project but I'm still stumped.
-jjmclell