I have just begun entering resource information into a fairly simple project. However, I cannot understand how MP handles the relationship between Work, Units, and Duration. For example, for a 1-week task, MP seems to be using 20 hours as the available time. So, if a person is assigned 24 hours, it calculates 120% as his Units and marks it overallocated. It is doing the same thing for all 3 people assigned to the task (e.g., 4 hrs comes up as 20%).
In another example, for a 2-week task duration (i.e. task due in 2 weeks and is resource-driven), there are 2 people each assigned 32 hrs. Yet, MP says that the Units for one are 100% and the other 50%. I cannot find a reason for this. I have checked and rechecked the calendar settings.
Can someone help? I may be missing something somewhere as I am a new user. Thanks.
In another example, for a 2-week task duration (i.e. task due in 2 weeks and is resource-driven), there are 2 people each assigned 32 hrs. Yet, MP says that the Units for one are 100% and the other 50%. I cannot find a reason for this. I have checked and rechecked the calendar settings.
Can someone help? I may be missing something somewhere as I am a new user. Thanks.