Change Project Duration

Status
Not open for further replies.

jimclark1947

Technical User
Jun 6, 2007
2
US
A project that was planned to end last week had new tasks assigned so it was rescheduled to end in July. After entering the new tasks I am trying to print the new Gantt chart but print preview only takes me out to the previou project end date.

In Project Information the End Date is shown correctly as the new date but it is grayed out and can't be adjusted.

I'm not finding anything in the page setup dialog that helps me with this problem. What do I need to change that will allow me to print the entire chart out to the new end date??

Thanks
 
File | Print, click on the radio button named "Dates" (lower left corner) and then select the start and finish dates you want to appear. Click on the Preview button and you should see your desired result.
 
Ah, thank you. I was sure I had seen something like this before but haven't used the program for over a year and forgot where to find it.
 