jimclark1947
Technical User
A project that was planned to end last week had new tasks assigned so it was rescheduled to end in July. After entering the new tasks I am trying to print the new Gantt chart but print preview only takes me out to the previou project end date.
In Project Information the End Date is shown correctly as the new date but it is grayed out and can't be adjusted.
I'm not finding anything in the page setup dialog that helps me with this problem. What do I need to change that will allow me to print the entire chart out to the new end date??
Thanks
In Project Information the End Date is shown correctly as the new date but it is grayed out and can't be adjusted.
I'm not finding anything in the page setup dialog that helps me with this problem. What do I need to change that will allow me to print the entire chart out to the new end date??
Thanks