Ive recently started using microsoft project for constrcution related schedules. My problem is as follows;
I have a proposed schedule completed for work that was supposed to begin in November of 2010, However the job did not begin until December. I want to change the start date of the proposed schedule to December and want all tasks to chance the same amount of days without having to change them individually.
Please can anyone tell me how to do this as otherwise it will be very time consuming.
Thanks
Damien
Ive recently started using microsoft project for constrcution related schedules. My problem is as follows;
I have a proposed schedule completed for work that was supposed to begin in November of 2010, However the job did not begin until December. I want to change the start date of the proposed schedule to December and want all tasks to chance the same amount of days without having to change them individually.