I'm getting an error trying to activate scheduled reports on a CCMA 6.0 "could not active schedule for (name of report) report." This occurs when I try to activate through Scheduled Events. When I try to activate it from the report itself, the error is "Unable to activate the schedule for (name of report): Cannot active job, Job has already active"

Doesn't matter if this is to a printer or to the Reports folder. I can run them adhoc and it will work, including to the Reports folder on the CCMA (I did share the folder as instructed).

Any ideas?
 
Found it...windows scheduler was not active.
 