I have a 5 day task. I right click the bar and get the split task cursor. I put the cursor at the halfway point in the bar, and drag to the right. This is what the help file says I should do. When I drag/drop, the task does not split it extends the bar to the right by the amount of time I moved it.
The split bar formatting is set to use a dotted line (.....) for split tasks but it is not doing so. On the task date, I see it is still 5 days and the end date increases to the last day I dragged it to.
So it seems the software is splitting the task but it is not showing it to me. Is this a setting issue in my options?
Thanks
The split bar formatting is set to use a dotted line (.....) for split tasks but it is not doing so. On the task date, I see it is still 5 days and the end date increases to the last day I dragged it to.
So it seems the software is splitting the task but it is not showing it to me. Is this a setting issue in my options?
Thanks