I have a resource that has 2 tasks. There is no dependency between the tasks.
Task A is 20 hours work, it can only be worked on 4 hours a day due to the nature of the work.
Task B is 40 hours work, it can be done any time, any day, and I want to use it to fill in after the Task A each day as they run in parallel.
I tried setting the resource to 50% on task A for units, but it will not schedule in the remainder of the day with Task B.
Any suggestions?