Is it possible to change the view of outline levels (or maybe change the actual outline level)? I have a project that has 4 outlines. I would like to view the information by the 4th outline level with the other outline levels underneath.
In other words, if I have a plan that looks like this:
-Demand Group 1
-Project 1
-Tower 1
-Bay 1
-Bay 2
+Tower 2
+Project 2
+Demand Group 2
Now I would like to look at the data in a different view
Like this ....
-Bay 1
+Project 3
+Project 4
+Bay 2
+Bay 3
etc..
Is that possible?
In other words, if I have a plan that looks like this:
-Demand Group 1
-Project 1
-Tower 1
-Bay 1
-Bay 2
+Tower 2
+Project 2
+Demand Group 2
Now I would like to look at the data in a different view
Like this ....
-Bay 1
+Project 3
+Project 4
+Bay 2
+Bay 3
etc..
Is that possible?