Can any one help me to solve this PM problem?

Status
Not open for further replies.

stoorrey

Vendor
Dec 25, 2009
1
GB
It’s a new Project.. The activities necessary for the completion of this are listed in the table below.

Activity, NorTime,CrashTime, NorCost,CrashCost, Predecessor
A.............3........2.........2200......2400......... -
B.............3........1.........2000......2700......... -
C.............2........3..........600......400 ....... -
D.............7........5.........2200......2500..........A
E.............5........4.........1000......1300..........B
F.............3........1.........2900......3900..........C
G.............5........2.........1300......2100.........D, E



(a)What is the project completion date?
(b) What is the total cost required for completing this
project on normal time?
(c) If you wish to reduce the time required to complete this project by one week, which activity should be crashed, and how much will this increase the total cost?
 