I have a question regarding the calendar view in MS Projects 2007. I would like to know if there is a way for the colors designated to a task on the gnatt chart to be transfered into the calendar view for each task.
I am able to change the color of the bar in calendar view, but it changes all of the tasks into the selected color. I would like to individualize the task colors on the calendar view. Is this possible? If so, how?