Hi,
Is there a way to get MS Project to calculate the Early Finish (or any other finish date) given:
- % complete on tasks
- duration or work
- todays date
say that todays date is X (say 1st Sep). The task's duration is say 10 days. It is 40% complete. I would like to see the Early Finish date show up as X+6 (i.e. 7th Sep).
I am using MS Project 2003.
I am sure there must be a way to make MS Project forecast the expected completion date given those parameters, but I haven't been able to work it out as of yet.
Anyone who has a hint ?
Thanks,
Cheers,
Dalgetty
Is there a way to get MS Project to calculate the Early Finish (or any other finish date) given:
- % complete on tasks
- duration or work
- todays date
say that todays date is X (say 1st Sep). The task's duration is say 10 days. It is 40% complete. I would like to see the Early Finish date show up as X+6 (i.e. 7th Sep).
I am using MS Project 2003.
I am sure there must be a way to make MS Project forecast the expected completion date given those parameters, but I haven't been able to work it out as of yet.
Anyone who has a hint ?
Thanks,
Cheers,
Dalgetty