Hi,
I've been informed by a contractor of a particular date that they are able to commence work for us. They will be doing work throughout the project but will be unable to begin until later next month. I want the tasks in MS project to reflect that but I do not want to constrain the individual tasks in case the work may be able to take place sooner if the contractor has more availability at a later date.
I entered some resource availability for the contractor and altered the units to 0% until the date they provided and then increased it to 100% from that date forward, Project confirms the auto-scheduled tasks as over-allocated and so when I use the task inspector to fix the issue it simply increases the duration of the task in to the contractors availability instead of moving the start date. Is there a better way for me to do this or should I just use a constraint? I really wanted to keep this project as fluid as possible.
thanks
I've been informed by a contractor of a particular date that they are able to commence work for us. They will be doing work throughout the project but will be unable to begin until later next month. I want the tasks in MS project to reflect that but I do not want to constrain the individual tasks in case the work may be able to take place sooner if the contractor has more availability at a later date.
I entered some resource availability for the contractor and altered the units to 0% until the date they provided and then increased it to 100% from that date forward, Project confirms the auto-scheduled tasks as over-allocated and so when I use the task inspector to fix the issue it simply increases the duration of the task in to the contractors availability instead of moving the start date. Is there a better way for me to do this or should I just use a constraint? I really wanted to keep this project as fluid as possible.
thanks